Ujjain Airport Expansion: Green Nod Deferred as EAC Seeks Faunal Study, Public-Hearing Answers

Ujjain airport expansion and environmental appraisal - original symbolic graphic
Original symbolic graphic: pcsmantra.com

Why in News

An Expert Appraisal Committee (EAC, Infrastructure-2) of the Union Environment Ministry has deferred its decision on the upgrade and expansion of the Ujjain (Datana) airport, citing inadequate responses to public-hearing concerns, the absence of a detailed faunal study and an incomplete assessment of the project's impact on local ecology - and sought additional details from the Airports Authority of India (AAI). The ~Rs 250-crore project is to be ready before the 2028 Simhastha Kumbh.

The Project

  • Expansion: the existing runway (1,077 m x 23 m) extended to 1,800 m x 45 m for ATR-72 and Q400 aircraft; a new 4,060 sq m terminal (peak-hour capacity 450 passengers), apron, isolation bay, ATC tower and fire station.
  • Capacity estimate: 20 scheduled commercial flights a day initially; ~7,300 aircraft movements and ~5,43,500 passengers a year.
  • Land: the MP government will acquire and hand over ~241 acres in addition to the existing airstrip, which is currently used for chartered operations.
  • Purpose: connectivity for the crores of pilgrims visiting the Mahakaleshwar temple and the religious-tourism circuit; an AAI-MP government MoU was signed on 1 November 2025.

The EAC's Objections

  • Schedule-I species dispute: AAI said no Schedule-I species were present in the 10-km buffer; the Ujjain DFO reported the presence of the Blackbuck, a Schedule-I species. The EAC directed a detailed fauna survey and a site-specific wildlife conservation plan in consultation with the forest department.
  • Public hearing ignored: at the 18 September hearing, locals and project-affected persons raised compensation, approach-road and agricultural-access issues - the EAC found these were not "addressed/replied properly"; it now wants a detailed report with budgetary provisions and a time-bound action plan.
  • DGCA distance rule: ToR compliance remains unshown - civil aviation guidelines generally restrict a new greenfield airport within an aerial distance of 150 km of an existing civilian airport, but proposals may be approved by the Central Government case by case after examining their impact on the existing airport; Indore is ~65 km away by road. AAI's position is that this is an upgrade (the MoU refers to sub-80-seater ATR-72 operations), not a greenfield airport.
  • Other: a revised Environmental Management Plan, a detailed tree survey and a compensatory plantation proposal with identified land.

Why It Matters

  • GS-III Environment/Infra: a live example of the EAC's role under the EIA Notification 2006, the value of public hearings and the development-conservation balance.
  • The Simhastha 2028 race: religious-tourism infrastructure versus process compliance - deadlines do not dilute compliance.
  • Wildlife protection: the Blackbuck is in Schedule I of the Wildlife (Protection) Act, 1972 - missing it in a survey is a serious compliance failure.

Prelims Practice Questions

Q1. The Blackbuck is listed in which Schedule of the Wildlife (Protection) Act, 1972?

(a) Schedule II

(b) Schedule III

(c) Schedule I

(d) Schedule V

Answer and Explanation

Answer: (c) Schedule I - the highest protection status; the Ujjain DFO reported its presence in the project area.

Q2. Within what aerial distance of an existing civilian airport does a greenfield airport proposal require examination of its impact on the existing airport and case-by-case Central Government approval?

(a) 75 km

(b) 100 km

(c) 150 km

(d) 200 km

Answer and Explanation

Answer: (c) 150 km. This is not an absolute ban; the policy provides for case-by-case Central Government approval.

Mains Practice Question

Q: "Environmental appraisal is not an obstacle to development but a guarantee of its quality." Comment in the context of the EAC's intervention in the Ujjain airport expansion. (250 words)

Outline: Introduction - the proposal and the EAC's deferral; the value of process - EIA 2006, public hearings, ToR compliance; the conservation dimension - Schedule-I species, faunal surveys, compensatory plantation; the development case - Simhastha 2028, connectivity; conclusion - time-bound compliance can serve both goals.

FAQ

Short answer: The EAC deferred clearance for the ~Rs 250-crore Ujjain (Datana) airport expansion: inadequate public-hearing responses, an incomplete faunal study (the DFO reported Blackbuck presence), unproven DGCA distance-rule compliance; a revised EMP and tree survey have been sought.

Q: Why did the EAC defer clearance?

Three main reasons: (1) AAI claimed no Schedule-I species, while the DFO reported the Blackbuck; (2) the 18 September public-hearing issues (compensation, approach road, farm access) were not properly answered; (3) ToR conditions - notably the DGCA 150-km rule - remain unproven.

Q: What does the project involve?

A 1,800 m x 45 m runway (ATR-72/Q400), a 4,060 sq m terminal (450 peak-hour passengers), apron and ATC tower; ~241 acres of additional land; capacity of ~5,43,500 passengers a year; target - before the 2028 Simhastha.

Q: What happens next?

AAI must submit a detailed fauna survey, a wildlife conservation plan in consultation with the forest department, a time-bound action plan (with budget) for public-hearing issues, a revised EMP and a tree survey with compensatory plantation; only then will appraisal proceed.