Published: 26 November 2026

In this article
Why in the News
On 25 November 2026 the Cabinet Committee on Economic Affairs (CCEA) approved a Second Container Terminal at Kamarajar Port Limited (KPL) under the Public Private Partnership (PPP) mode on a Design, Build, Finance, Operate and Transfer (DBFOT) basis. The estimated cost of the PPP component is Rs 4,288.26 crore including GST. [1]
Reading the Cost Correctly
Rs 4,288.26 crore is the cost of the PPP component and it includes GST: Rs 2,429.32 crore for Phase I and Rs 1,858.94 crore for Phase II. The selected concessionaire will arrange this investment. [1]
The project proposal separately indicates an estimated dredging cost of Rs 450 crore, to be borne by KPL. So do not call Rs 4,288.26 crore the all-inclusive project cost. According to the release there is no financial implication for the Government of India for the PPP component. [1]
What the DBFOT Model Is
Under DBFOT a private concessionaire designs, builds, finances and operates the project and transfers it at the end of the concession. It recovers its investment through user charges under the Concession Agreement and the tariff framework. Selection is by a transparent, open global bid. The concession period is 40 years, including a 48-month construction period. [1]
Terminal Capacity and Phases
The terminal will be 900 m long with a 30 m berth width and an 18 m design draft. Annual capacity is 2.0 million TEUs (Twenty-foot Equivalent Units, the standard unit for measuring containers). Phase I has 1.1 million TEUs and Phase II has 0.9 million, so 1.1 + 0.9 = 2.0 million. [1]
Phase I is to be completed within 24 months of the Date of Award of Concession, with commercial operations from the 25th month. Phase II construction runs from the 25th to the 48th month, with full commercial operations from the 49th month. The terminal is designed for vessels of up to 24,346 TEUs and 400 m length overall. [1]
The Demand Case: KPL Figures
In FY 2025-26 KPL handled 49.08 million tonnes of cargo and 1,008 vessels, including more than 7 lakh TEUs of containers. The existing container terminal has an installed capacity of 0.8 million TEUs and handled about 0.7 million, a utilisation of about 88%. Over five years India's container traffic grew at about 7% CAGR and KPL's at about 9.9%. [1]
KPL was formerly Ennore Port Limited. It is one of the 12 Major Ports and, according to PIB, is wholly owned by the Chennai Port Authority. It handles coal, petroleum, LNG, LPG, containers, automobiles and general cargo. [1]
Expected Impact
According to the release, the added capacity gives the Chennai-Ennore industrial region and the southern hinterland another gateway for EXIM cargo. An 18 m draft eases direct calls by large vessels and reduces dependence on foreign hub ports and feeder costs. Employment is estimated at about 750 persons, directly and indirectly, during construction, and about 800 additional persons in the operational phase. These are expected effects, not proven results. [1]
Way Forward
Analysis: Success will depend on competitive bidding, timely environmental and other clearances before the bid due date, dredging, and road and rail links to the port. The tariff framework must balance private returns with user costs. The release's own schedule has Phase I due within 24 months of the Date of Award of Concession, so the benefits are not immediate. [1]
Prelims Practice Questions
Question 1. Consider the following statements:
Statement 1: The estimated cost of the PPP component of the Second Container Terminal at Kamarajar Port is Rs 4,288.26 crore including GST.
Statement 2: The Rs 450 crore dredging cost is included in this Rs 4,288.26 crore and will be borne by the concessionaire.
Which of the statements given above is/are correct?
Answer and Explanation
Answer: (b)
Statement 1 is correct: the PPP component is estimated at Rs 4,288.26 crore including GST.
Statement 2 is incorrect: the Rs 450 crore dredging cost is indicated separately and is to be borne by KPL.
Question 2. Consider the following statements about Kamarajar Port Limited:
Statement 1: It was formerly known as Ennore Port Limited.
Statement 2: The proposed annual capacity of the new terminal is 2.0 million TEUs.
Statement 3: The concession period is 40 years.
Which of the statements given above is/are correct?
Answer and Explanation
Answer: (d)
Statement 1 is correct: PIB says KPL was formerly Ennore Port Limited.
Statement 2 is correct: 2.0 million TEUs (1.1 million in Phase I and 0.9 million in Phase II).
Statement 3 is correct: the DBFOT concession period is 40 years including 48 months of construction.
Mains Practice Question
Discuss the role and limits of the PPP model in expanding India's container port capacity, with reference to the Second Container Terminal at Kamarajar Port. (250 words, 15 marks)
Answer outline
Introduction: Explain the need for capacity from container traffic growth and KPL's utilisation.
Main body: Add the DBFOT structure, private finance, user charges, the separately funded public dredging cost, and clearance and tariff challenges. Do not call the project cost all-inclusive.
Conclusion: Conclude with transparent bidding, timely clearances and connectivity.
Sources
Frequently Asked Questions (FAQ)
What does Rs 4,288.26 crore cover?
The estimated PPP component including GST: Rs 2,429.32 crore for Phase I and Rs 1,858.94 crore for Phase II.
Who bears the dredging cost?
The project proposal indicates an estimated Rs 450 crore dredging cost to be borne by KPL, separate from the PPP component.
How big will the terminal be?
2.0 million TEUs a year in total: 1.1 million in Phase I and 0.9 million in Phase II.
Download this article: PDF